# Construction Loan Drawdowns: Stages and Cash-flow Example

Plan construction-stage interest and rent overlap with a worked example, a blank cash-flow sheet and links to lender progress-payment instructions.

Plan construction-stage interest and rent overlap with a worked example, a blank cash-flow sheet and links to lender progress-payment instructions.

Construction drawdowns release parts of a loan as building work progresses. To plan the cash you need, record the balance already drawn, the expected time until the next draw and any rent you will still pay. Your contract and lender set the actual payment process.

Start with the public example below, then try the interest during build calculator. The tool shows a total before its optional detailed-results form. It does not assess loan eligibility or recommend a lender.

Illustrative arithmetic, prepared 8 September 2026. This is a calculator example, not a lender offer or an industry-standard payment schedule.

Inputs: a $500,000 construction balance released over 12 months; a constant 6.5% annual rate; no opening land-loan balance, fees, offset or principal repayments. Rent is a made-up $2,000 per month. The calculator’s default stage shares are 12%, 17%, 25%, 23% and 23%, with 2, 3, 3, 3 and 1 months at each balance.

## Who approves a progress payment?

## Cash-flow worksheet: interest plus rent

## Check these assumptions with your lender

## What happens if a stage is delayed?

### Bankwest Construction Loan: Progress-payment Documents

### Construction Loans Explained: How They Work in Australia (2026)

#### Construction Loan vs Home Loan

#### Granny Flat Rules NSW

#### How to Finance a Granny Flat

#### Calculate Borrowing Power

#### Calculate Borrowing Power

#### Calculate Borrowing Power

#### Calculate Borrowing Power

#### Calculate Borrowing Power

#### Calculate Borrowing Power

## Key Points

- Does the loan already include a drawn balance for the land?
- Which contract stages and amounts will be paid from the loan?
- How is interest charged, and what happens if a stage takes longer?
- Which fees, borrower contributions and insurance documents apply?
- How will a variation affect the approved funds and remaining cash?
- Repayment
- Interest During Build
- Total Cost ★
- Stamp Duty
- How Construction Loans Work

## Frequently Asked Questions

### Who approves a progress payment?

Ask your lender which invoice, authority and inspection they need at each stage. For example, Bankwest’s progress-payment instructions require authority from the borrower for each payment and say a progress inspection may be needed. Other lenders can have different steps.

### What happens if a stage is delayed?

Extend the time at the relevant balance and add the extra rent. For example, one extra month at a $270,000 drawn balance and 6.5% is $1,462.50 in this simplified model. With $2,000 rent, that month adds $3,462.50 before other costs. This is arithmetic, not a forecast of a building delay.

---
*Source: [RooLoans](https://rooloans.com/guides/progress-drawdown-explained)*